25. The Forge as the Record of Open Work and a Frozen Planning Graph

Date: 2026-10-11

Status

Accepted. Amended by ADR-0029 (a step whose acceptance is unmet reopens).

Context

ADR-0019 tracked the migration to cordanaLLM/imago as a typed dependency graph under planning/, routed by imago plan route. The forge tracked the product in parallel: issues under milestones, checked on every pull request.

Two records of open work drifted apart:

  • The overlay went stale. planning/routing.json listed step-archetype-upstream and step-archetype-switch as open for 26 days after cordanaLLM/praetor#54 and #37 had delivered them.
  • Open steps had no issue. Three open steps were visible only to a reader of planning/, so no milestone counted them.
  • Planned items had no home at all. Accepted ADRs (0009, 0010, 0016, 0017, 0018) and principle 9.1 promise 18 items that neither the graph nor the forge listed.
  • The copied milestone file drifted. .github/milestones.json named 30 flavors where the forge milestone names 44.

Decision

  1. The forge is the record of open work. Every open unit is an issue under a milestone. The maintainer decided this on 2026-10-11 (paraphrased: one source per fact; the open steps become issues, the in-repo graph is frozen as a migration record).
  2. The planning graph is frozen. planning/plan.json, its projections and planning/routing.json stay as the record of the migration. No step is added. The overlay changes only to mark an open step done, with the pull request as evidence.
  3. The three open steps are carried by issues: step-lefthook-verify by #80, step-app-hardening by #81 and step-aegis-pair by #46. The overlay names the issue in the evidence field.
  4. Planned items live under the milestone "Post-1.0 roadmap". One issue per source records the promise and the state of the tree: #82 to #86 for the five ADRs, #87 for principle 9.1, #73 for an item of an earlier plan. Such an issue is a tracked home, not a scheduled unit; order and scope are decided after the 1.0 release.
  5. The router code stays. pkg/planning, imago plan validate, imago plan route and the route_plan MCP tool are unchanged. Whether the fleet reuses the package is decided outside this repository. AGENTS.md no longer lists imago plan route --ready in the working sequence, because the ready set of open work is now the forge.
  6. .github/milestones.json is copied from the forge again, including the new milestone and the note on the milestone that was closed without an issue.

Consequences

  • Positive: one place answers what is open. A milestone count is the count of open work.
  • Positive: every public promise of an accepted ADR has an issue that states what exists.
  • Negative: the overlay is updated by hand when one of the three issues closes. Three updates remain, and the file names the issue for each.
  • Negative: nothing checks .github/milestones.json against the forge yet. A drift check is planned as its own unit.
  • Neutral: ADR-0019 is not rewritten. Its decision 4 describes how the migration was tracked; this record states what holds from 2026-10-11 on.

References

  • ADR-0019: the planning graph and its router.
  • docs/tools/planning-graph.md: the files, the routing policy and the table of carried steps.
  • GOVERNANCE.md: milestones and the copied milestone file.